What Order Does a Kitchen Remodel Happen In? From Demolition to Punch List

The sequence of a kitchen remodel step by step, including where flooring goes relative to cabinets, cabinet lead time, and when countertops can be templated.

All posts

Published

The short answer

Design and ordering come first, then demolition, rough plumbing and electrical, inspection, drywall and paint, flooring (before or after cabinets, depending on the material), cabinet installation, countertop template, countertop installation, backsplash, appliances and plumbing trim, then the punch list. San Diego contractors publish about 6 to 14 weeks of construction once demolition starts.

Construction time
About 6 to 14 weeks once demolition starts; cosmetic refreshes 2 to 4 weeks (San Diego guides, 2026)
Cabinet lead time
About three weeks of production after approved drawings at Swell's workshop; vendor guides quote 4 to 12 weeks
Countertops
Templated after the cabinets are set; template-to-install time is set by the fabricator
Permit
No-plan permit for a same-footprint kitchen; plan check for a moved wall or new sink
Flooring
Hardwood and tile usually before cabinets; floating vinyl after

Before demolition: design, permit, order

The kitchen is finished on paper before anything is torn out. Layout, cabinet drawings, appliance models, tile, counters and fixtures are chosen first. Then the permit: in the City of San Diego a same-footprint kitchen with no added fixtures can use a no-plan permit, and the combined plumbing, mechanical and electrical permit is $440.82 per dwelling unit. Moving a wall or adding a sink sends the job to plan check.

Cabinets are ordered next, as the gate item. Swell builds frameless cabinets in its own San Diego workshop with about three weeks of production after approved drawings; vendor guides published in 2026 quote 4 to 6 weeks for semi-custom lines and 8 to 12 weeks for fully custom shops. Demolition waits until the cabinets have a delivery date.

Demolition, rough-in and inspection

Demolition removes the old cabinets, counters and flooring. Plumbers and electricians then rough in the new lines while the walls are open: circuits for the range and dishwasher, island power, moved supply and drain lines. On a San Diego slab, relocating a drain is quoted at about $3,000 to $8,000 per line in local guides published in 2026. The rough-in inspection happens before the walls close.

Drywall, paint and the flooring decision

Drywall is patched, primed and painted while the room is empty. Then the question homeowners ask most: before or after the cabinets?

Hardwood and tile usually go in first. The floor runs under the cabinets, toe kicks land at the right height, and a future layout change does not expose bare subfloor. The trade-off is more material and protecting the new floor for the rest of the job. Floating floors such as luxury vinyl plank usually go in after, because heavy cabinets pin a floating floor. Dishwasher and range openings are then sized to the finished floor so appliances can be pulled later.

Cabinets, then template, then counters

Cabinets are set level and plumb, scribed to the walls and fastened. Only when the boxes are fixed and the sink and cooktop are on site does the countertop fabricator template. The time from template to installation is set by the fabricator and written into the schedule. The kitchen has no counters during that gap; a temporary plywood top is common. Backsplash tile waits for the counters.

Backsplash, appliances, trim and punch

After the counters, the backsplash is tiled and grouted, the plumber sets the sink and dishwasher, the electrician installs outlets and under-cabinet lighting, and appliances slide in last. Where a permit applies, the final inspection follows, then a punch-list walkthrough: doors aligned, drawers adjusted, caulk, touch-up paint.

Where schedules slip

San Diego contractors publish about 6 to 14 weeks of construction in 2026; the slips come from a short list.

  • ◆Selections made after demolition, so trades wait on a tile or a faucet.
  • ◆Cabinets ordered after demolition instead of before.
  • ◆Hidden conditions in older homes: galvanized pipe, undersized wiring, past water damage.

Questions homeowners ask

Should flooring go in before or after kitchen cabinets?

Hardwood and tile usually before, running under the cabinets for a continuous floor and correct toe-kick heights. Floating floors such as luxury vinyl plank usually after, because cabinets would pin the floor. Either way the written scope names the finished floor height so appliances can be removed later.

How long do kitchen cabinets take to arrive?

Swell's production is about three weeks after approved drawings, because the cabinets are built in its own San Diego workshop. Vendor guides published in 2026 quote 4 to 6 weeks for semi-custom lines and 8 to 12 weeks for fully custom shops. Order before demolition.

How long after cabinets are installed do countertops go in?

The fabricator templates once the cabinets are set and the sink and cooktop are on site, then cuts and installs on a schedule the fabricator sets and the contractor writes into the project plan. Backsplash tile waits for the counters, so the gap is part of the sequence.

How long does a kitchen remodel take in San Diego?

San Diego contractor guides published in 2026 put construction at about 6 to 14 weeks once demolition starts, with cosmetic refreshes at 2 to 4 weeks. Design, cabinet production and any permit review come before that, so plan on several months from first meeting to finished kitchen.

Sources and review date

Market ranges, not a quote. Your price is set at a free in-home estimate. Last reviewed .

Plan your project

Have a project in mind?

Skip the research rabbit hole. Get a realistic planning range, or book a free on-site consultation with one accountable, licensed team: Swell Contracting, CSLB B #970145.